Case Studies

Putting your FCA into action

  • Challenge:
    • A 5M GSF health campus in South Florida had challenges converting their FCA-defined deferred maintenance need into executable projects. Leadership supported the findings of the FCA through additional funding, but facility management and project delivery teams struggled to define actionable steps to address the need.
  • Halcyon’s Impact:
    • Halcyon deployed the Renewal Asset Management Program to convert need into projects. In a cradle-to-grave approach, Halcyon evaluated the performance of mechanical, electrical and plumbing systems, developed projects based on the deficiencies identified, and managed the execution of all funded work.
  • Outcome:
    • In one building, the FCA stated there was $46M in deferred maintenance. Halcyon determined $6.3M of reinvestment would resolve deficiencies in 34 assets and various distribution systems.  
Ramp InventoryRAMP Stabilization StatusRAMP Reinvestment Recommendations
SystemAssetCountUnstable Assets% UnstableFCA Deferred MaintenanceRAMP Project CostRAMP Funding RecommendationComments
MechanicalAHUs, Ductwork & Distribution12975%$ 20,820,224$ 4,510,300FundRefurbish (10) AHUs, resolve downstream distribution & reseal ductwork
Boilers200%$ 435,128$ –Do Not FundBoilers stable; no recommendations
Heat Exchangers300%$ –$ –Do Not FundHeat exchangers stable; no recommendations
CHW Pumps5120%$ 187,275$ 15,000FundReplace CHWP 1
HHW Pumps4125%$ 111,099$ 40,000FundReplace HHWP 5
Exhaust Fans2500%$ 807,112$ 10,000FundInstall roof guardrail; Exhaust fans operational; no recommendations
Fume Hoods400%$ –$ 57,000FundRepair fume hoods
ControlsN/AN/AN/A$ 3,548,782$ 490,000FundUpgrade controls (new front end & tie in critical assets; provide graphics)
PlumbingDCW Pumps2150%$ 102,450$ 20,000FundReplace DCWP 1
Sewer/Sump Pumps500%$ 165,753$ –Do Not FundPumps stable; no recommendation
Water Heater100%$ 12,473$ –Do Not FundWater heater stable; no recommendation
Air Compressor66100%$ 112,384$ 60,000FundInstall rotary air compressors and dryer for control air
Expansion Tank600%$ 22,567$ –Do Not FundExpansion tanks stable; no recommendation
Plumbing Fixtures (Sinks/Showers/Toilets)N/AN/AN/A$ 2,729,617$ –Do Not FundDefer until future renovations
DistributionN/AN/AN/A$ 4,323,182$ 327,000FundResolve findings from pipe scan assessments
ElectricalSwitchgear200%$ –$ 46,500FundEquipment operating; maintenance overdue & requires electrical shutdowns
Main Transformers100%$ –$ 49,500FundEquipment operating; maintenance overdue & requires electrical shutdowns
Transfer Switches9444%$ 154,620$ 102,000FundReplace (2) transfer switches
Bus Ducts300%$ 2,043,361$ –Do Not FundBus ducts stable; no recommendations
Motor Control Center2150%$ 495,086$ 220,000FundDecommission MCC & replace with main distribution panel
Transformers/Panels/Breakers10000%$ 2,373,949$ 350,000FundRecent IR scan deficiencies to be resolved with replacement of OR electrical panels
Emergency LightingN/AN/AN/A$ 786,898$ –Do Not FundDefer until future renovations
LightingN/AN/AN/A$ 5,276,521$ –Do Not FundDefer until future renovations
WiringN/AN/AN/A$ 2,175,906$ –Do Not FundDefer until future renovations
1922312%$ 46,684,386$ 6,297,300

Improve reliability and ROI by integrating refurbishment projects into your deferred maintenance strategy

  • Challenge:
    • A recent FCA for a hospital indicated all air handling units were deferred and in need of replacement for $2.9M. Facility leaders prioritized the replacement of 5 critical units serving 10 operating rooms, the emergency department and the east and west wings of the hospital. After a lengthy design, cost estimates for the replacement projects escalated to $10.5M and would require extensive disruption to a 24/7 facility. 
  • Halcyon’s Impact:
    • Halcyon’s assessments determined that while these units were underperforming, they met the capacity requirements for the building. It was recommended to refurbish the units at a fraction of the cost, time, and disruption to replace them.
  • Outcome:
    • For 36% of the replacement cost for 5 AHUs, Halcyon was able to refurbish 10 AHUs.  Beyond the cost avoidance, all AHUs were refurbished in less than 12 months, compared to the multi-year commitment needed to design, procure, and construct new units. 
Project ComparisonsFCA Defined NeedReplacement ProjectRenewal Project
ScopeReplace 10 AHUsReplace 5 AHUs
New units, no change in capacity
Refurbish 10 AHUs
Achieve original design performance
CostProject Budget$2.9M$10.5M$3.8M
$/Asset$0.29M$2.1M$0.38M
% Annual Funding5.0%17%6.3%
ScheduleDuration (months)N/A3612
Design123
Procurement127
Construction122
DisruptionLong outages requiring temporary AHUsShort outages only requiring spot coolers

Advance your maintenance staffing profile, reduce reliance on contractors and decrease operating costs

  • Challenge:
    • A university was faced with a reactive and expensive maintenance portfolio. They could not determine a clear solution without understanding how they compared to peers and what the root causes were to address the problems.
  • Halcyon’s Impact:
    • Halcyon analyzed and benchmarked in-house and outsourced resources to identify areas of inefficiencies and service issues. The analysis evaluated operating costs, outsourcing reliance, contract management, compensation rates, staff coverage, trades mix, shift coverage, and the preventative maintenance program.
  • Outcome:
    • An implementation strategy was provided to increase the in-house staff, recruit for specialized positions and eliminate specific contracts and outsourced tasks for an overall cost savings to operations. 
Benchmark IndicatorMetricBenchmark StatusCurrent StateBenchmarkRecommended State
Maintenance Operating Costs$/GSFOperating costs are high$7.72$5.30$6.66
Reactive Maintenance% ReactiveHigh reactive work indicates increased service disruption64%20%30%
Outsourcing ReliancePurchased Services as a % of Total SpendMost preventative maintenance and repair work is outsourced at premium costs83%45%69%
Staff CoverageGSF/FTEMaintenance team is understaffed94,78076,06067,267
Trades Mix% GeneralistsMajority of trades staff are generalists and cannot respond to technical issues effectively69%32%30%
Shift Coverage% 1st ShiftLack of off-shift staff leads to an increase in vendor reliance90%72%72%
Supervision RatioFTE/
Supervisor
Current supervision ratios are adequate6.06.36.1
Halcyon Facilities Group logo
Contact Us 330-760-4113
50032 Red Run Rd. 
Marcellus, MI 49067
Service Disabled Veteran Owned Small Business logo
U.S. Small Business Administration:
Halcyon Facilities Group is certified by the Veteran Small Business Certification Program (VetCert) at SBA as a Service-Disabled Veteran Owned Small Business (SDVOSB)
Veteran Owned Small Business Certification & Registration (unitedstatesbusinessregistration.us)
© 2025 Halcyon Facilities Group